October 2019
1-5 Olive York Way, Brunswick West
The Grove is well advanced and nearing completion. The building structure has now been completed, and we are currently peeling back the scaffolding showcasing the beautiful simple architectural elements of the building. Internally, all the contractors are working cohesively to deliver the project to the highest standard in a timely and orderly manner. Kitchens, bathrooms, plastering and tiling are a work in progress, as well as all the wonderful shared spaces including the green gardens, gymnasium, spa and the multitude of entertainment zones.
Moving forward, we will provide you with some helpful hints to guide you through the settlement process.
Our team have a dedicated contact person as the point of contact for all matters relating to the settlement.
We will advise of settlement timing, assist with finance enquiries, as well as conduct bank valuation and purchaser inspections.
In relation to the programme, the status is as follows:
Programme
The key programme items are as follows:
Stage Status
- Site set up works Completed
- Bulk excavation Completed
- Basement works Completed
- Structure works Completed
- Services rough in In progress
- Window glazing In progress
- Facade cladding In progress
- Internal fit out works In progress
- Finishing works In progress
- Title registration
- Occupancy permit
- Ready to settle
Settlement Date
Settlement is anticipated for early 2020. We will keep you updated as we get closer to this date.
February 2019
1-5 Olive York Way, Brunswick West
Due to the size and scale of the earthworks programme, The Grove is a couple of months behind program.
We have now completed all the excavation and retention works for the triple basement. It’s been a slow journey with the 12,000m2 basement. We are now in the transition phase with the basement contractor handing over to the structural contractor. We are expecting the ground floor slab to be completed by Easter.
In relation to the program, the status is as follows:
Construction Program
Stage Status
1. Site set up works Completed
2. Bulk excavation Completed
3. Basement works Completed
4. Structure works Commencing
5. Services rough in
6. Window glazing
7. Facade cladding
8. Internal fit out works
9. Finishing works
10. Title registration
11. Occupancy permit
12. Ready to settle
Settlement Date
Settlement is anticipated for early 2020.
We will keep you updated as we get closer to this date.