January 2020
244-246 Pascoe Vale Rd, Essendon
Happy New Year!
The facade rendering is nearing completion as the builder progresses towards the final stages of construction.
It is expected that construction will complete around February and settlement is targeted to be around March 2020 (exact timeline is dependent on titles registration and issuance of occupancy permit).
If you have any queries regarding the project, please contact your agent or contact us at info@dynamicresidential.com.au
November 2019
244-246 Pascoe Vale Rd, Essendon
Construction is now at the lock up stage.
The builder has estimated that they will physically complete construction by December 2019 and settlement will be around Q1, 2020 (exact timeline is dependent on titles registration and issuance of occupancy permit).
If you have any queries regarding the project, please contact your agent or contact us at info@dynamicresidential.com.au
August 2019
244-246 Pascoe Vale Rd, Essendon
Construction is now at the Frame stage.
The builder has estimated that they will physically complete construction by the end of 2019 and settlement will be around Q1, 2020 (exact timeline is dependent on titles registration and issuance of occupancy permit).
If you have any queries regarding the project, please contact your agent or contact us at info@dynamicresidential.com.au
May 2019
244-246 Pascoe Vale Rd, Essendon
Construction works have now progressed to Frame stage.
The builder has estimated that they will physically complete construction by the end of 2019 and settlement will be around Q1, 2020 (exact timeline is dependent on titles registration and issuance of occupancy permit).
If you have any queries regarding the project, please contact your agent or contact us at info@dynamicresidential.com.au
April 2019
244-246 Pascoe Vale Rd, Essendon
Construction works have now progressed to Frame stage.
The builder has estimated that they will physically complete construction at the beginning of Q4,2019 with settlements to follow thereafter (exact timeline is dependent on titles registration and issuance of occupancy permit).
If you have any queries regarding the project, please contact your agent or contact us at info@dynamicresidential.com.au
March 2019
244-246 Pascoe Vale Rd, Essendon
Construction work at Queens Terraces is currently at the slab stage.
It is projected that physical completion will take place by Q4,2019 with settlements to follow thereafter (exact timeline is dependent on titles registration and issuance of occupancy permit).
If you have any queries regarding the project, please contact your agent or contact us here.
January 2019
244-246 Pascoe Vale Rd, Essendon
Plumbing works are still ongoing at Queens Terraces and the builder aims to complete the slab stage by mid to late February.
It is projected that physical completion will take place by Q4,2019 with settlements to follow thereafter (exact timeline is dependent on titles registration and issuance of occupancy permit).