The Peak Construction Progress

December 2019

141-149 La Trobe St, Melbourne

 

The building structural core on track for completion before Christmas 2019.
The internal fit out of apartments is on track for completion to level 20 by the end of this year and all structural floors will be complete by the end of January. This means the tower crane will come down shortly thereafter, in February 2020.
Permanent power and water supply are already connected to the building.

The building program is on track for completion in Q2 2020, with settlement of apartments to occur thereafter.

Please note that the above anticipated timing is subject to favourable conditions and/or unforeseen delays. We will continue to provide you with regular construction updates leading up to settlement.

Please see a few recent photos of The Peak site.

August 2019

141-149 La Trobe St, Melbourne

 

Works on site are progressing well and the construction phase is now at around level 22.

The developer estimates that physical completion will take place Q2 2020, with settlements to follow thereafter (exact timeline is dependent on titles registration and issuance of occupancy permit).

Should you have any queries, please contact your agent or email to info@dynamicresidential.com.au

April 2019

141-149 La Trobe St, Melbourne

 

The Level 4 deck has been poured with Level 5 commencing in the 2nd week of April. The building’s core has now reached Level 8.

The developer estimates that physical completion will take place around Q1-Q2 of 2020, with settlements to follow thereafter (exact timeline is dependent on titles registration and issuance of occupancy permit).

Should you have any queries, please contact your agent or contact us here.

January 2019

141-149 La Trobe St, Melbourne

The basement and ground works have been completed and the building is now taking shape above ground.

The builders Hamilton Marino are working diligently to complete each level. It is anticipated that The Peak will be completed in approximately Q1-Q2,2020, with settlements to follow thereafter (exact timeline is dependent on titles registration and issuance of occupancy permit).